Lincoln Common Construction Progress Update

Go Back

Please note: In conformance with the Project Community Agreement, Lincoln Common construction work will continue through extended hours and on weekends to make up for lost time due to weather delays.

In addition, traffic signalization improvements will continue through the week of February 25th at the intersection of Lincoln, Halsted and Fullerton.

Week of 2/11/19

  • Exterior metal panel install on both buildings will continue
  • Punch list and final cleaning of lower floors in the A2 South Tower will be completed this week
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower complete
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A1 North Tower continues
  • A1 retail façade storefront and GFRC panel install will continue
  • Site work in the plaza concrete planters, fountain work, and trellis install will continue
  • Work on the decorative trellis in the plaza temp shoring removal; painting of trellis will be in the spring
  • Traffic signalization improvements continue at the intersection of Lincoln, Halsted and Fullerton start this week
  • Parking garage elevator replacement work continues

Week of 2/18/19

  • Exterior metal panel install on the South tower should complete this week, weather permitting; metal panel work on the North tower will continue
  • Punch list and final cleaning of middle floors in the A2 South Tower will continue
  • Punch list and final cleaning of lower floors in the A1 North Tower will continue
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A1 North Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower
  • Site work in the plaza concrete planters, fountain work, and trellis install will continue
  • Traffic signalization improvements continue at the intersection of Lincoln, Halsted and Fullerton continues
  • Parking garage elevator replacement work continues

Week of 2/25/19

  • Exterior metal panel install on the A1 North tower will continue
  • Punch list and final cleaning of middle floors in the A2 South Tower will continue
  • Punch list and final cleaning of lower floors in the A1 North Tower will continue
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A1 North Tower continues
  • A1 retail façade storefront and GFRC panel install will continue
  • Site work in the plaza concrete planters, fountain work, and trellis install will continue
  • Traffic signalization improvements continue at the intersection of Lincoln, Halsted and Fullerton continues
  • Parking garage elevator replacement work continues

Thank you for your continued patience as Lincoln Common comes to life!