Lincoln Common Construction Progress Update

Go Back

With partial construction of the A2 South Tower complete, move-ins on floors 2-13 began yesterday at The Apartments at Lincoln Common! Learn more about The Apartments at Lincoln Common in Crain's Chicago Business exclusive preview. Please see below for planned construction activity over the coming weeks. Thank you for your continued support as Lincoln Common comes to life and stay tuned for upcoming retailer openings and event announcements!

Please note: In conformance with the Project Community Agreement, Lincoln Common construction work will continue through extended hours and on weekends to make up for lost time due to weather delays.

Week of 4/1/19

  • Exterior metal panel install on North building will continue
  • South Tower occupancy floors 2-13 starts this week
  • Main plaza opened for public use – remaining landscaping, fountain and final painting of trellis work
  • Punch list and final cleaning of upper floors in the A2 South Tower continue
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A1 North Tower continues
  • Traffic signalization improvements at the intersection of Lincoln, Halsted and Fullerton continue
  • Parking garage elevator replacement work continues
  • Parking garage structural repairs continue
  • Site utility work at the Orchard and Fullerton intersection will continue

Week of 4/8/19

  • Exterior metal panel install on North Tower will be completed this week
  • Main plaza opened for public use – remaining landscaping, fountain and final painting of trellis work
  • Punch list and final cleaning of upper floors in the A2 South Tower continue
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A1 North Tower continues
  • Traffic signalization improvements at the intersection of Lincoln, Halsted and Fullerton continue
  • Parking garage elevator replacement work continues
  • Parking garage structural repairs continue
  • A1 and A2 retail 2nd floor green roof install starts this week
  • Site utility work at the Orchard and Fullerton intersection will continue

Week of 4/15/19

  • Main plaza opened for public use – remaining landscaping and fountain work
  • Punch list and final cleaning of Upper floors in the A2 South Tower complete this week
  • Interior cabinet and finish installation on the upper floors in the A1 North Tower continues
  • Traffic signalization improvements at the intersection of Lincoln, Halsted and Fullerton continue
  • Parking garage elevator replacement work continues
  • Parking garage structural repairs continue
  • A1 and A2 retail 2nd floor green roof install continues
  • Site utility work at the Orchard and Fullerton intersection will continue

Week of 4/22/19

  • Main plaza opened for public use – remaining landscaping work
  • Punch list and final cleaning of upper floors in the A2 South Tower complete this week
  • Upper floors in the A1 North Tower complete and ready for turn over
  • Traffic signalization improvements at the intersection of Lincoln, Halsted and Fullerton continue
  • Parking garage elevator replacement work continues
  • Parking garage structural repairs continue
  • A1 and A2 retail 2nd floor Green roof install continues
  • Site utility work at the Orchard and Fullerton intersection will continue