Belmont Village – Lincoln Park Construction Progress Update - August 28, 2017

Just a reminder that sheeting along the alley on the northwest corner of the Belmont Village project site will take place this Wednesday 8/30 and Thursday 8/31 and this work will close a small portion of the alley each day (view map). The alley will still be accessible from the north entrance and residents on the southernmost portion of the alley (running east/west) will still have access to their homes.
More

Belmont Village Demolition & Construction Update - June 29, 2017

  • Underpinning of the west and north neighboring properties has been completed
  • Limited excavation of the old foundation and earth retention preparation has now been completed
  • Installation of the earth retention system is expected to begin the week of July 17th and will continue through the end of the year as we excavate for the underground parking garage
  • Fullerton Ave. and Orchard St. sidewalks and parking lanes have been closed and will remain closed for the duration of the project

Thank you for your continued patience and understanding as we work through these critical first steps of construction. Should you have questions or would like additional information, please contact Adam Hamilton of Belmont Village or Mark Bussey of W.E. O'Neil. More