Belmont Village Demolition & Construction Update - June 29, 2017

  • Underpinning of the west and north neighboring properties has been completed
  • Limited excavation of the old foundation and earth retention preparation has now been completed
  • Installation of the earth retention system is expected to begin the week of July 17th and will continue through the end of the year as we excavate for the underground parking garage
  • Fullerton Ave. and Orchard St. sidewalks and parking lanes have been closed and will remain closed for the duration of the project

Thank you for your continued patience and understanding as we work through these critical first steps of construction. Should you have questions or would like additional information, please contact Adam Hamilton of Belmont Village or Mark Bussey of W.E. O'Neil. More

Professional Building Facade Restoration to Begin Week of May 8th

The façade of the Dental Professional Building at 2358 North Lincoln Avenue will be incorporated into a new, mixed-use structure. This historic façade will be dismantled and preserved through a detailed inventory of all components. The preserved façade will be rebuilt into the new structure and will include all of the existing details. More

Belmont Village Demolition & Construction Update - May 1, 2017

  • Demolition was completed on March 3, 2017.
  • The City of Chicago building permit was issued on March 24, 2017.
  • Inclinometer installation in the alley was completed on April 6, 2017.
  • Today, Monday, May 1, 2017, we are scheduled to start the underpinning work on the foundations of the adjoining properties to the North and West of the site. This work is currently scheduled to be completed in approximately 5 weeks.
  • Excavation and site work is expected to begin once the underpinning work is completed.
  • Fullerton Ave. and Orchard St. sidewalks and parking lanes have been closed and will remain closed for the duration of the project.

Thank you for your continued patience and understanding as we work through these critical first steps of construction. Should you have questions or would like additional information, please reach out to the Senior Living or Construction representatives on the Contact page.  More