Belmont Village Construction Progress Update

Posted on March 29, 2019


Week of 4/1/19

  • Mechanical, electrical, and plumbing throughout building continues
  • Rock and tape drywall
  • Cornice install
  • Painting interior walls
  • Flooring install
  • Installing millwork/cabinets
  • Installing ceiling grid
  • Installing doors
  • Installing kitchen equipment
  • Waterproofing exterior slabs
  • Brick washing exterior

Week of 4/8/19

  • Mechanical, electrical, and plumbing throughout building continues
  • Rock and tape drywall
  • Cornice install
  • Painting interior walls
  • Flooring install
  • Installing millwork/cabinets
  • Installing ceiling grid
  • Installing doors
  • Installing kitchen equipment
  • Waterproofing exterior slabs
  • Topping slabs
  • Brick washing exterior

Week of 4/15/19

  • Mechanical, electrical, and plumbing throughout building continues
  • Rock and tape drywall
  • Cornice install
  • Painting interior walls
  • Flooring install
  • Installing millwork/cabinets
  • Installing ceiling grid
  • Installing doors
  • Waterproofing exterior slabs
  • Topping slabs
  • Brick washing exterior

Week of 4/25/19

  • Mechanical, electrical, and plumbing throughout building continues
  • Cornice install
  • Painting interior walls
  • Flooring install
  • Installing millwork/cabinets
  • Installing ceiling grid
  • Installing doors
  • Waterproofing exterior slabs
  • Topping slabs
  • Brick washing exterior
  • Sidewalks, curbs, and gutter

Thank you for your continued patience as Belmont Village Lincoln Park comes to life. Should you have questions about the development, please contact Adam Hamilton of Belmont Village or Mike Gabel, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.