Belmont Village Construction Progress Update

Go Back

Week of 4/29/19

  • Mechanical, electrical, and plumbing trim
  • Painting interior walls
  • Flooring/tile install
  • Installing millwork/cabinets
  • Installing ceiling grid
  • Installing doors
  • Brick washing exterior
  • Pouring topping slabs
  • Sidewalk curbs

Week of 5/6/19

  • Mechanical, electrical, and plumbing trim
  • Painting interior walls
  • Flooring/tile install
  • Installing millwork/cabinets
  • Installing ceiling grid
  • Installing doors
  • Pouring topping slabs
  • Install street lights

Week of 5/13/19

  • Mechanical, electrical, and plumbing trim
  • Painting interior walls
  • Flooring/tile install
  • Installing millwork/cabinets
  • Installing ceiling grid
  • Installing doors
  • Sidewalks

Week of 5/20/19

  • Mechanical, electrical, and plumbing trim
  • Painting interior walls
  • Flooring/tile install
  • Installing millwork/cabinets
  • Installing ceiling grid
  • Installing doors
  • Landscaping

Thank you for your continued patience as Belmont Village Lincoln Park comes to life. Should you have questions about the development, please contact Adam Hamilton of Belmont Village or Mike Gabel, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.