The Orchard Condominiums Construction Progress Update

Posted on January 28, 2020

Please see below for construction work planned for The Orchard Condominiums over the coming weeks. Note: Tower crane removal is scheduled to begin the week of February 17. During this time, Orchard Street between Kemper and Fullerton will be closed to vehicular traffic. Please see the below logistics plan for details. We will distribute a reminder closer to this date or let you know if the schedule changes due to weather.

Should you have questions about construction of The Orchard, please contact Construction Project Manager, Ted Gilbane. For sales inquiries, please contact Sotheby's International Realty at Info@TheOrchardLincolnPark.com.

Week of 1/27

  • Overhead mechanical, electrical and plumbing work on upper floors
  • Precast installation including wide load trucking deliveries
  • Exterior building envelope work
  • Interior build-out

Week of 2/3

  • Overhead mechanical, electrical and plumbing work on upper floors
  • Precast installation including wide load trucking deliveries
  • Exterior building envelope work
  • Interior build-out

Week of 2/10

  • Precast installation including wide load trucking deliveries
  • Exterior building envelope work
  • Interior build-out

Week of 2/17

  • Tentative shutdown of Orchard Street between Kemper and Fullerton for tower crane removal
  • Precast installation including wide load trucking deliveries
  • Exterior building envelope work
  • Interior build-out

Week of 2/24

  • Tentative shutdown of Orchard Street between Kemper and Fullerton for tower crane removal
  • Precast installation including wide load trucking deliveries
  • Exterior building envelope work
  • Interior build-out