Please see below for construction work planned for The Orchard Condominiums over the coming weeks. Note that the skip hoist is scheduled to be removed from the building on Monday, April 6th. All activities listed below will take place on-site, with the exception of trucks entering and leaving the site with the removed hoist equipment.

Should you have questions about construction of The Orchard, please contact Construction Project Manager, Ted Gilbane. For sales inquiries, please contact Sotheby's International Realty at Info@TheOrchardLincolnPark.com.

Week of 3/23

  • Interior build out on floors 1 – 7
  • Window installation on Level 1
  • Installation of cast stone & ceilings at terraces
  • Installation of metal panels by swing staging
  • Precast patching with 80’ Boom Lift

Week of 3/30

  • Interior build out on floors 1 – 7
  • Window installation on level 1
  • Installation of cast stone & ceilings at terraces
  • Installation of metal panels by swing staging
  • Precast patching with 80’ Boom Lift
  • Tentative site work start

Week of 4/6

  • Interior build out on floors 1 – 7
  • Installation of cast stone & ceilings at terraces
  • Installation of metal panels by swing staging
  • Precast patching with 80’ Boom Lift
  • Dismantling and removal of Skip Hoist
  • Tentative site work

Week of 4/13

  • Interior build out on floors 1 – 7
  • Installation of cast stone & ceilings at terraces
  • Precast patching with 80’ Boom Lift
  • Tentative site work
  • Installation of precast and windows at skip hoist leave out

Week of 4/20

  • Interior build out on floors 1 – 7
  • Installation of cast stone & ceilings at terraces
  • Tentative site work
  • Installation of precast and windows at skip hoist leave out