The Orchard Condominiums Construction Progress Update

Posted on March 05, 2020

Please see below for construction work planned for The Orchard Condominiums over the coming weeks. Should you have questions about construction of The Orchard, please contact Construction Project Manager, Ted Gilbane. For sales inquiries, please contact Sotheby's International Realty at Info@TheOrchardLincolnPark.com.

This week

  • Fullerton sidewalk re-opened with overhead protection
  • Interior build out on floors 1 – 5
  • Window Installation on level 6 & 7
  • Installation of cast stone & ceilings at terraces
  • Installation of metal panels by swing staging

Week of 3/9

  • Interior build out on floors 1 – 5
  • Window Installation on Level 6 & 7
  • Installation of cast stone & ceilings at terraces
  • Installation of metal panels by swing staging

Week of 3/16

  • Interior build out on floors 1 – 6
  • Window Installation on Level 7
  • Installation of cast stone & ceilings at terraces
  • Installation of metal panels by swing staging

Week of 3/23

  • Interior build out on floors 1 – 7
  • Installation of cast stone & ceilings at terraces
  • Installation of metal panels by swing staging
  • Weather permitting exterior site work start

Week of 3/30

  • Interior build out on floors 1 – 7
  • Installation of cast stone & ceilings at terraces
  • Weather permitting exterior site work start