The Orchard Condominiums Construction Progress Update

Posted on July 26, 2019

Please see below for construction work planned for The Orchard Condominiums over the coming weeks. Should you have questions about construction of The Orchard, please contact Construction Project Manager, Ted Gilbane. For sales inquires, please contact Cadey O'Leary of Sotheby's International Realty.

For more information about The Orchard, please visit TheOrchardLincolnPark.com. To choose the updates that you'd like to receive about Lincoln Common, please update your preferences at LincolnCommon.com.

Week of 7/22

  • Complete pouring of slab on grade
  • Complete (2) north side foundation walls
  • Rebar trucking ongoing
  • Concrete trucking and pumping ongoing (jersey barrier bump out for outriggers)

Week of 7/29

  • Continue pouring foundation walls
  • Rebar trucking ongoing
  • Concrete trucking

Week of 8/5

  • Continue pouring foundation walls
  • Rebar trucking ongoing
  • Concrete trucking

Week of 8/12

  • Continue/Complete foundation wall pours
  • Possible pouring of B1 slab which would require bumping out of jersey barriers to accommodate outriggers
  • Concrete trucking
  • Rebar trucking
  • Mechanical systems construction in support of concrete

Week of 8/19

  • Pour B1 slab
  • Concrete trucking
  • Rebar trucking
  • Mechanical systems construction in support of concrete