The Orchard Condominiums Construction Progress Update

Posted on October 29, 2019

Please see below for construction work planned for The Orchard Condominiums over the coming weeks. Should you have questions about construction of The Orchard, please contact Construction Project Manager, Ted Gilbane. For sales inquiries, please contact Sotheby's International Realty at Info@TheOrchardLincolnPark.com or visit the sales gallery at 2315 N. Lincoln Avenue.

Week of 10/28

  • Installation of pre-cast panels at roof penthouses
  • Interior framing
  • Overhead mechanical, electrical and plumbing work

Week of 11/4

  • Installation of pre-cast panels at roof penthouses
  • Interior framing
  • Overhead mechanical, electrical and plumbing work
  • Sidewalk work inside the project boundary

Week of 11/11

  • Installation of pre-cast on south half of building
  • Interior framing
  • Overhead mechanical, electrical and plumbing work
  • Sidewalk work inside the project boundary

Week of 11/18

  • Installation of pre-cast on south half of building
  • Interior framing
  • Overhead mechanical, electrical and plumbing work

Week of 11/25

  • Installation of pre-cast on south half of building
  • Interior framing
  • Overhead mechanical, electrical and plumbing work