The Orchard Condominiums Construction Progress Update

Posted on August 22, 2019

Please see below for construction work planned for The Orchard Condominiums over the coming weeks. Should you have questions about construction of The Orchard, please contact Construction Project Manager, Ted Gilbane. For sales inquires, please contact Cadey O'Leary of Sotheby's International Realty.

For more information about The Orchard, please visit TheOrchardLincolnPark.com. To choose the updates that you'd like to receive about Lincoln Common, please update your preferences at LincolnCommon.com.

Week of 8/19

  • Preparation and pouring of the 1st floor slab
  • Backfilling against foundation walls (during the week and Saturday)

Week of 8/26

  • Preparation and pouring of the 2nd floor slab
  • Interior buildout on garage levels

Week of 9/2

  • Preparation and pouring of 3rd floor slab
  • Preparation of the 4th floor slab
  • Interior buildout on garage levels

Week of 9/9

  • Preparation and pouring of 4th floor slab
  • Preparation and pouring of the 5th floor slab
  • Interior buildout on garage levels

Week of 9/16

  • Preparation and poring of the 6th floor slab
  • Utility work sewer connections on Orchard Street. At times, barricades may bump out of current installation but traffic will remain open. Gilbane to flag as required.
  • Interior buildout on garage levels