Lincoln Common Construction Update - January 14, 2019

Go Back

Lincoln Common, January 13, 2019

Please note: In conformance with the Project Community Agreement, Lincoln Common construction work will continue through extended hours and on weekends to make up for lost time due to weather delays.

Week of 1/14/19

  • Exterior metal panel install on both buildings will continue
  • Punch list and final cleaning of lower floors in the A2 South Tower has started
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A1 North Tower continues
  • We completed taking down the A1 North Tower exterior temp elevator hoist last week
  • Interior wall framing and drywall continues in the A1 North Tower
  • A1 retail façade storefront and GFRC panel install will continue
  • Site work in the plaza concrete planters, fountain work, and trellis install will continue
  • Work on the decorative trellis in the plaza continues
  • Parking garage elevator replacement work continues

Week of 1/21/19

  • Exterior metal panel install on both buildings will continue
  • Punch list and final cleaning of lower floors in the A2 South Tower will continue
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A1 North Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower
  • A1 retail façade storefront and GFRC panel install will continue
  • Site work in the plaza concrete planters, fountain work, and trellis install will continue
  • Work on the decorative trellis in the plaza continues
  • Parking garage elevator replacement work continues

Week of 1/28/19

  • Exterior metal panel install on both buildings will continue
  • Punch list and final cleaning of lower floors in the A2 South Tower will continue
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A1 North Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower
  • A1 retail façade storefront and GFRC panel install will continue
  • Site work in the plaza concrete planters, fountain work, and trellis install will continue
  • Work on the decorative trellis in the plaza continues
  • Parking garage elevator replacement work continues

Happy New Year and Thank You for your continued patience as Lincoln Common comes to life!