Week of 1/21/19

  • Mechanical, electrical, and plumbing throughout building continues
  • Exterior masonry west and east arcade
  • Setting showers in resident bathrooms
  • Skim coat ceilings in resident units
  • Insulating interior walls
  • Rock and tape drywall
  • Walk-in cooler delivery

Week of 1/28/19

  • Mechanical, electrical, and plumbing throughout building continues
  • Exterior masonry east and west alley
  • Setting showers in resident bathrooms
  • Skim coat ceilings in resident units
  • Insulating interior walls
  • Rock and tape drywall

Week of 2/4/19

  • Mechanical, electrical, and plumbing throughout building continues
  • Setting showers in resident bathrooms
  • Skim coat ceilings in resident units
  • Insulating interior walls
  • Rock and tape drywall

Week of 2/11/19

  • Mechanical, electrical, and plumbing throughout building continues
  • Setting showers in resident bathrooms
  • Skim coat ceilings in resident units
  • Insulating interior walls
  • Rock and tape drywall