Lincoln Common Update - April 2, 2018

Posted on April 02, 2018

We would like to inform you that Denice Bocek, McCaffery/Hines Development and Community Liaison, has moved on to take advantage of a new career opportunity. We offer Denice a sincere thank you for her years of service to this project, and wish her well in her new endeavor!

Moving forward, Malcolm Craig will serve as the McCaffery/Hines Development and Community Liaison. A McCaffery employee for over two years, Malcolm holds a bachelor's from Virginia Tech and an MBA in Real Estate from the University of Colorado. Malcolm will serve as the bridge between the development team and the community, and can be reached at (312) 784-2791 or mcraig@mccafferyinterests.com.

Please see below for the latest Lincoln Common construction activity schedule. To recover time lost due to weather, we may work overtime and extended hours. Thank you for your continued patience and understanding, and please visit LincolnCommon.com for additional project details.

Week of 4/2/18

  • Concrete work and lower level glass installation on the A2 South Tower will continue
  • Concrete work and lower level glass installation on the A1 North Tower will continue
  • Foundation work will start for the on-grade retail space along Lincoln Avenue
  • Vertical concrete work will continue on D Building North of the garage

Week of 4/9/18

  • Concrete work and lower level glass installation on the A2 South Tower will continue
  • Concrete work and lower level glass installation on the A1 North Tower will continue
  • Foundation work will continue for the on-grade retail space along Lincoln Avenue
  • Vertical concrete work will continue on D Building North of the garage
  • Site utility storm and water service work will be taking place on Lincoln Avenue through the week of the 16th

Week of 4/16/18

  • Concrete work and lower level glass installation on the A2 South Tower will continue
  • Concrete work and lower level glass installation on the A1 North Tower will continue
  • Foundation work will continue for the on-grade retail space along Lincoln Avenue
  • Concrete work will be completed this week on D Building North of the garage
  • Site utility storm and water service work will be taking place on Lincoln Avenue this week