Lincoln Common Construction Updates & Notice of Work Sunday 11/4

Go Back

Lincoln_Common_-_View_2-20181102-141736.jpg#asset:1015

In conformance with the Project Community Agreement, Lincoln Common construction work will continue through extended hours and on weekends to make up for lost time due to weather delays. The following work will take place within the apartment towers this Sunday, November 4:

  • A1 North tower window installation at top of building; skip hoist will be running for this work.

Pavement Replacement
Reminder: Phase 4 of curb and sidewalk pavement replacement surrounding the Lincoln Common project site will continue according to the schedule shared on October 2nd. Please see this logistics plan for additional details.

Phase 4: October 29 through November 8 Curbs and sidewalks on east side of Lincoln Avenue in front of construction site entrance

Lincoln Avenue Parking Garage Main Entrance Now Open
Construction activity around the main entrance to the Lincoln Avenue parking garage is complete and the main entrance to the garage is now open for all traffic. The southern entrance is now closed.

Thank you for your continued patience and understanding as Lincoln Common comes to life. Please visit LincolnCommon.com for additional project details.