Lincoln Common Progress Update & Notice of Work Sunday 10/21

Go Back

Lincoln_Common_-_View_2-20181018-105700.jpg#asset:1006

In conformance with the Project Community Agreement, Lincoln Common construction work will continue through extended hours and on weekends to make up for lost time due to weather delays. The following work will take place within the apartment towers this Sunday, October 21:

  • ComEd will be on site to shut down the power on the A1 North tower for testing and inspections
  • Electricians will be on site working in the A1 North tower assisting ComEd
  • Window wall installation work at the top of the A2 South tower will continue
  • Roofing on the 2nd floor A1 North retail area will continue
  • Elevator installers on site working on the A2 South tower elevators

Curb and Sidewalk Work
Replacement of curb and sidewalk pavement surrounding Lincoln Common will continue per the previously shared schedule. Please see this logistics plan for closure details.

Alley Work
Pending final City approval, additional work within the alley behind the Lincoln Common parking garage will be conducted Wednesday, October 24 through Friday, November 2. Please see this logistics plan for closure details. We will notify you if there are any changes to this schedule.

Construction Progress Update

Week of 10/22/18

  • Glass installation on the A2 South tower continues at the top of the building
  • Glass installation on the A1 North tower continues; install of the pool and spa at the top of the building continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South tower continues
  • Interior wall framing and drywall continues in the A1 North tower
  • A2 retail façade work is making good progress with masonry work
  • A1 retail façade framing, sheathing and waterproofing are underway
  • Site work in the plaza, concrete planters and fountain work will continue
  • E2 single-story retail building in front of the garage has been completed
  • Parking garage deck repair work will continue along with first floor renovation work
  • Roofing work on the North 2nd floor retail area continues

Week of 10/29/18

  • Glass installation on the A2 South tower scheduled for completion this week, pending weather
  • Glass installation on the A1 North tower continues; install of the pool and spa at the top of the building continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South tower continues
  • Interior wall framing and drywall continues in the A1 North tower
  • A2 retail façade work is making good progress with masonry work
  • A1 retail façade framing, sheathing and waterproofing are underway
  • Site work in the plaza, concrete planters and fountain work will continue
  • Parking garage deck repair work will continue along with first floor renovation work
  • Roofing work on the North 2nd floor retail should be completed this week

Week of 11/5/18

  • Glass installation on the A1 North Tower continues; install of the pool and spa at the top of the building continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South tower continues
  • Interior wall framing and drywall continues in the A1 North tower
  • A2 retail façade work is making good progress with masonry work
  • A1 retail façade framing, sheathing and waterproofing are underway
  • Site work in the plaza, concrete planters and fountain work will continue
  • Parking garage deck repair work will continue along with first floor renovation work

Thank you for your continued patience as Lincoln Common comes to life! Please visit LincolnCommon.com for additional project details.