Lincoln Common Construction Progress Update & Notice of Work Sunday, 11/18

Go Back

Lincoln_Common_-_View_2-20181116-100053.jpg#asset:1018

In conformance with the Project Community Agreement, Lincoln Common construction work will continue through extended hours and on weekends to make up for lost time due to weather delays. The following work will take place within the apartment towers this Sunday, November 18:

  • North Tower electricians will be working inside the building
  • South Tower electricians will be working inside the building

Construction Progress Update

Week of 11/19/18

  • Glass installation on the A2 South Tower continues at the top of the building
  • Glass installation on the A1 North Tower continues; install of the pool and spa at the top of the building continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower
  • A1 retail façade storefront and GFRC panel install has started
  • Site work in the plaza concrete planters and fountain work will continue, and the plaza trellis install has started
  • Parking garage deck repair work will continue along with first-floor renovation work
  • Roofing work on the North 2nd floor retail area should be completed this week

Week of 11/26/18

  • Glass installation on the A2 South Tower scheduled for completion this week, pending weather
  • Glass installation on the A1 North Tower continues; install of the pool and spa at the top of the building will continue
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower
  • A1 retail façade storefront and GFRC panel install will continue
  • Site work in the plaza concrete planters and fountain will continue; plaza trellis install will continue
  • Parking garage deck repair work will continue along with first-floor renovation work

Week of 12/3/18

  • Glass installation on the A1 North Tower continues; install of the pool and spa at the top of the building should be completed this week
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower
  • A1 retail façade Storefront and GFRC panel install will continue
  • Site work in the plaza concrete planters and fountain will continue; plaza trellis install will continue
  • Parking garage deck repair work will continue along with first-floor renovation work

Thank you for your continued patience as Lincoln Common comes to life! Please visit LincolnCommon.com for full project details.