Lincoln Common Construction Progress Update - May 4, 2018

Posted on May 04, 2018

Lincoln_Common_-_View_1-20180424-104031.jpg#asset:932

Please see below for the latest update on the construction of Lincoln Common. Thank you for your continued patience and understanding as we work through these critical steps of construction. For additional project details, please visit LincolnCommon.com.

Week of 5/7/18

  • Concrete work and lower level glass installation on the A2 South Tower will continue
  • Interior wall framing and drywall installation will begin in the South A2 tower
  • Concrete work and lower level glass installation on the A1 North Tower will continue
  • Foundation work will continue for the on-grade retail space along Lincoln Avenue
  • D building exterior masonry and metal stud framing will continue
  • The current phase of site utility work on Lincoln in front of the C and D building will be completed

Week of 5/14/18

  • Concrete work and lower level glass installation on the A2 South Tower will continue
  • Interior wall framing and drywall installation will continue in the A2 tower South
  • Concrete work and lower level glass installation on the A1 North Tower will continue
  • Foundation work will be completed for the on-grade retail space along Lincoln Avenue
  • Structural steel install will get started for the single-story retail structure at Lincoln and Fullerton
  • A pedestrian canopy will be installed on Lincoln Avenue from the existing boiler building to Fullerton; see attached logistics plan for work shown in the Red Clouded area.
  • Vertical concrete work will continue on D Building North of the garage
  • D building exterior masonry and metal stud framing will continue
  • Site utility work on Lincoln Avenue in front of the parking garage will begin

Week of 5/21/18

  • Concrete work and lower level glass installation on the A2 South Tower will continue
  • Interior wall framing and drywall will continue in the A2 South tower
  • Concrete work and lower level glass installation on the A1 North Tower will continue
  • Interior wall framing and drywall will begin in the A1 North tower
  • Structural steel install will continue for the single-story retail structure at Lincoln and Fullerton
  • D Building exterior masonry work will begin
  • Site utility storm and water service work will be taking place on Lincoln Avenue this week