Lincoln Common Construction Progress Update - June 8, 2018

Posted on June 08, 2018

Please see below for the latest construction activity schedule, and thank you for your continued patience and understanding as we bring Lincoln Common to life. Visit LincolnCommon.com for additional project details.

Lincoln_Common_-_View_2-20180608-141138.jpg#asset:941

Week of 6/11/18

  • Concrete work at the top of the building and glass installation on the A2 South Tower will continue
  • Interior wall framing and drywall will continue in the A2 South tower
  • Concrete work at the top of the building and glass installation on the A1 North Tower will continue
  • Interior wall framing and drywall will have started in the A1 North Tower
  • Structural steel install will continue for the single-story retail structure at Lincoln and Fullerton
  • D Building exterior masonry work will continue
  • Excavation and concrete foundation work will get started on the E2 single-story retail building in front of the garage to the west of the entrance
  • Steel and bar joist install will start on the E1 single-story retail building in front of the garage to the east of the entrance

Week of 6/18/18

  • Concrete work at the top of the building and glass installation on the A2 South Tower will continue
  • Interior wall framing and drywall will continue in the A2 South Tower
  • Concrete work at the top of the building and glass installation on the A1 North Tower will continue
  • Interior wall framing and drywall will have started in the A1 North Tower
  • Structural steel install will be completed for the single-story retail structure at Lincoln and Fullerton
  • D Building exterior masonry work will continue
  • Concrete foundation work will continue on the E2 single-story retail building in front of the garage to the west of the entrance
  • Steel and bar joist install will continue on the E1 single-story retail building in front of the garage to the east of the entrance
  • C building interior demolition work will continue

Week of 6/25/18

  • Concrete work at the top of the building and glass installation on the A2 South Tower will continue
  • Interior wall framing and drywall will continue in the A2 South Tower
  • Concrete work at the top of the building and glass installation on the A1 North Tower will continue
  • Interior wall framing and drywall will have started in the A1 North Tower
  • Structural steel install will be completed for the single-story retail structure at Lincoln and Fullerton
  • D Building exterior masonry work will continue
  • C building interior demolition work will continue

Week of 7/2/18

  • Concrete work at the top of the building will be completed on the A2 South Tower
  • Glass installation on the A2 South Tower will continue
  • Interior wall framing and drywall will continue in the A2 South Tower
  • Concrete work at the top of the building and glass installation on the A1 North Tower will continue
  • Interior wall framing and drywall will have started in the A1 North Tower
  • D Building exterior masonry work will continue
  • C building interior demolition work will continue

As an advance notice, we are currently planning to remove the A2 South Tower crane the week of July 18th. This activity will require the closure of Lincoln Avenue to complete. This date is a target for now and is subject to adjustment. Actual closure dates and rerouting details will be shared when the schedule is confirmed.