Lincoln Common Construction Progress Update - July 6

Posted on July 06, 2018

Lincoln_Common_-_View_2-20180705-143612.jpg#asset:964

Week of 7/9/18

  • Interior wall framing and drywall will continue in the A2 South Tower
  • Concrete work at the top of the A1 North Tower and glass installation will continue
  • Interior wall framing and drywall will continue in the A1 North Tower
  • D Building exterior masonry work will continue including the historic façade
  • Concrete foundation work will continue on the E2 single-story retail building
  • Exterior framing will start on the E1 single-story retail building
  • C building interior demolition work will continue

Week of 7/16/18

  • Glass installation on the A2 South Tower will continue; install of the pool and spa at the top of the building will continue
  • Interior wall framing, drywall, cabinet and finish installation on the lower floors in the A2 South Tower will continue
  • Concrete work at the top of the building and glass installation on the A1 North Tower will continue
  • Interior wall framing and drywall will continue in the A1 North Tower
  • D Building exterior masonry work will continue including the historic façade
  • Concrete foundation work will continue on the E2 single-story retail building
  • Exterior framing will Continue on the E1 single-story retail building
  • C building interior demolition work will be completed; exterior restoration of the façade will continue

Week of 7/23/18

  • Removal of the A2 South Tower Crane will begin the morning of Tuesday, July 24th and be completed by end of day Friday, July 27th. This process will require the closure of Lincoln Avenue from the main parking garage entrance south to Belden Avenue during this time. See this logistics plan for details.
  • Glass installation on the A2 South Tower will continue and install of the mechanical systems at the top of the building will start
  • Interior wall framing and drywall, cabinet and finish installation will continue in the A2 South Tower
  • Concrete work at the top of the building and glass installation on the A1 North Tower will continue
  • Interior wall framing and drywall will have started in the A1 North Tower
  • D Building exterior masonry work will continue including the historic façade
  • C Building Exterior restoration of the façade will continue

Thank you for your continued patience and understanding as construction of Lincoln Common progresses. Please visit LincolnCommon.com for additional project details.