Lincoln Common Construction Progress Update - Feb. 16, 2018

Posted on February 16, 2018

Lincoln-Common-View-2-February-16th-2018-1208-pm.jpg#asset:896

We will be working overtime and extended hours to recover time lost due to weather. Thank you for your continued patience and understanding as we work through these critical steps of construction. For additional project details, please visit LincolnCommon.com.

Week of 2/19/18

  • The A2 South Tower water service work on Orchard should be completed this week
  • A1 North Tower water service on Fullerton should be complete, pending city water department completion of the water main tap work in street. Note: This may require water shut off for a short period of time. Please contact the City of Chicago with any questions.
  • Concrete work on the A2 South Tower will continue
  • Concrete work on the A1 North Tower will continue
  • Vertical concrete work will continue on D Building North of the Garage

Week of 2/26/18

  • Concrete work on the A2 South Tower will continue
  • Concrete work on the A1 North Tower will continue
  • Vertical concrete work will continue on D Building North of the Garage

Week of 3/5/18

  • Concrete work on the A2 South Tower will continue
  • Concrete work on the A1 North Tower will continue
  • Vertical concrete work will continue on D Building North of the Garage

Lincoln-Common-View-1-February-16th-2018-1144-am.jpg#asset:897