Replacement of curb, alley and sidewalk pavement surrounding Lincoln Common will continue through October 9th, per the previously shared schedule. Please see this logistics plan for location for sidewalk closure details.

Week of 9/24/18

  • Glass installation on the A2 South Tower continues at the top of the building
  • Glass installation on the A1 North Tower continues; install of the pool and spa at the top of the building continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower
  • A2 retail façade work is making good progress with masonry work
  • A1 retail façade framing, sheathing and waterproofing are under way
  • Site work in the plaza concrete planters and fountain work has started
  • D Building north of the garage is complete with exception of punch list items
  • E2 single-story retail building in front of the garage masonry will be completed and storefront install will start this week
  • C Building sidewalk canopy has been removed and storefront installation is almost completed
  • Parking garage deck repair work will continue along with first floor renovation work.

Week of 10/1/18

  • Glass installation on the A2 South Tower continues at the top of the building
  • Glass installation on the A1 North Tower continues; install of the pool and spa at the top of the building continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower, cabinet and finish installation on the lower floors will continue
  • A2 retail façade work is making good progress with masonry work; storefront installation will start this week
  • A1 retail façade framing, sheathing and waterproofing will continue
  • Site work in the plaza concrete planters and fountain work will continue
  • D Building north of the garage is complete with exception of punch list items
  • E2 single-story retail building in front of the garage storefront will be completed this week
  • C Building work will be complete with the exception of punch list work
  • Parking Garage Deck repair work will continue along with first floor renovation work

Week of 10/8/18

  • Glass installation on the A2 South Tower continues at the top of the building
  • Glass installation on the A1 North Tower continues; install of the pool and spa at the top of the building continues
  • Interior wall framing, drywall, cabinet and finish installation on the upper floors in the A2 South Tower continues
  • Interior wall framing and drywall continues in the A1 North Tower, cabinet and finish installation on the lower floors will continue
  • A2 retail façade masonry work will continue, storefront installation will continue
  • A1 retail façade framing, sheathing and waterproofing will continue
  • Site work in the plaza concrete planters and fountain work will continue
  • D Building north of the garage is complete with exception of punch list items
  • E2 single-story retail building in front of the garage will be complete with the exception of punch list items
  • C Building work will be complete with the exception of punch list work
  • Parking Garage Deck repair work will continue along with the first floor renovation work

Thank you for your continued patience and understanding as construction of Lincoln Common progresses. Please visit LincolnCommon.com for additional project details.