Week of 10/29/18

  • Mechanical, electrical, and plumbing throughout building continues
  • 5th floor interior metal stud wall framing
  • Exterior masonry
  • Elevator install
  • Finish roofing

Week of 11/5/18

  • Mechanical, electrical, and plumbing throughout building continues
  • 5th floor interior metal stud wall framing
  • Exterior masonry
  • Window install
  • Elevator install

Week of 11/12/18

  • Mechanical, electrical, and plumbing throughout building continues
  • 6th floor interior metal stud wall framing
  • Exterior masonry
  • Window install
  • Elevator install

Week of 11/19/18

  • Mechanical, electrical, and plumbing throughout building continues
  • 6th floor interior metal stud wall framing
  • Exterior masonry
  • Window install

Thank you for your continued patience and understanding as we work through construction. Should you have questions or would like additional information about the BelmontVillage project, please contact Adam Hamilton of Belmont Village or Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.