Belmont Village Construction Progress Update - November 19, 2018

Go Back

BV_111918.jpg#asset:1020


Week of 11/26/18

  • Mechanical, electrical and plumbing throughout building continues
  • Exterior masonry north and west alley
  • 7th floor interior metal stud wall framing
  • Penthouse metal panel enclosure
  • Construct elevators

Week of 12/3/18

  • Mechanical, electrical and plumbing throughout building continues
  • Exterior masonry east and west alley
  • 7th floor interior metal stud wall framing
  • Penthouse metal panel enclosure
  • Rock/tape drywall
  • Construct elevators

Week of 12/10/18

  • Mechanical, electrical and plumbing throughout building continues
  • Exterior masonry east, west and south alley
  • Rock/tape drywall
  • Install windows

Week of 12/17/18

  • Mechanical, electrical and plumbing throughout building continues
  • Exterior masonry east, west and south alley
  • Rock/tape drywall
  • Install windows

Thank you for your continued patience we complete these construction phases. Should you have questions or would like additional information about the Belmont Village project, please contact Adam Hamilton of Belmont Village or Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.