Belmont Village Construction Progress Update - May 11, 2018

Posted on May 11, 2018

BV_051118.jpeg#asset:934

Week of 5/14/18

  • Pour ground floor deck
  • Frame and pour foundation walls
  • Excavate tunnel connecting to Lincoln Common site

Week of 5/21/18

  • Frame and pour columns and walls to second floor
  • Frame deck on second floor

Week of 5/28/18

  • Frame and pour deck on second floor
  • Start lower level two masonry walls
  • Frame and pour column to third floor

Thank you for your continued patience and understanding as construction progresses. Should you have questions or would like additional information about the Belmont Village project, please contact Adam Hamilton of Belmont Village or Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.