Week of 3/26/18

  • Frame and pour concrete foundation walls
  • Frame and pour lower level 1 floors
  • Install waterproofing on the sheeting
  • Lower level 1 plumbing and electrical work (in concrete slab)

Week of 4/2/18

  • Frame and pour concrete foundation walls
  • Frame and pour lower level 1 floors
  • Install waterproofing on the sheeting
  • Lower level 1 plumbing and electrical work (in concrete slab)

Week of 4/9/18

  • Frame and pour concrete foundation walls
  • Frame and pour lower level 1 floors
  • Install waterproofing on the sheeting
  • Lower level 1 plumbing and electrical work (in concrete slab)

Week of 4/16/18

  • Remove tier 1 earth retention
  • Frame and pour ground level floors
  • Install waterproofing on sheeting

Thank you for your continued patience and understanding as we work through these critical first steps of construction. Should you have questions or would like additional information about the Belmont Village project, please contact Adam Hamilton of Belmont Village or Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.