Belmont Village Construction Progress Update - March 2, 2018

Posted on March 02, 2018

BV_image002_030218.png#asset:911

The concrete operation is completing slab on grade. Underground plumbing and underground electrical work is complete. Removal of lower level 2 earth retention to begin the week of 3/5/18.

Week of 3/5/18

  • Removal of tier 2 earth retention
  • Install waterproofing on the sheeting

Week of 3/12/18

  • Removal of tier 2 earth retention
  • Frame and pour concrete foundation walls
  • Install waterproofing on the sheeting

Week of 3/19/18

  • Frame and pour concrete foundation walls
  • Frame and pour lower level 1 floor
  • Install waterproofing on the sheeting

Week of 3/26/18

  • Frame and pour concrete foundation walls
  • Frame and pour lower level 1 floor
  • Install waterproofing on the sheeting
  • In slab and building plumbing and electrical to begin

Thank you for your continued patience and understanding as we work through these critical first steps of construction. Should you have questions or would like additional information about the Belmont Village project, please contact Adam Hamilton of Belmont Village or Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.