Belmont Village Construction Progress Update - April 17, 2018

Posted on April 17, 2018

belmont_041718.jpg#asset:928

Week of 4/16/18

  • Remove tier 1 earth retention
  • Frame perimeter foundation walls
  • Install waterproofing on sheeting

Week of 4/23/18

  • Remove tier 1 earth retention
  • Frame perimeter foundation walls
  • Install waterproofing on sheeting

Week of 4/30/18

  • Install waterproofing on sheeting
  • Form ground floor deck

Week of 5/7/18

  • Pour ground floor deck
  • Frame and pour columns and shear walls
  • Prepare for site utility work

Thank you for your continued patience and understanding as we work through this phase of construction. Should you have questions or need additional information about the Belmont Village project, please contact Adam Hamilton of Belmont Village of Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.