Belmont Village Construction Progress Update - 8/7/18

Posted on August 07, 2018

BVimage003.jpg#asset:976

This Week

  • Roof pour (topping out!)
  • Exterior metal stud wall begins
  • Mechanical, electrical, and plumbing lines complete through 1st floor

Week of 8/13/18

  • Penthouse erection and enclosure
  • Mechanical, electrical, and plumbing throughout building continues
  • Boilers and other rooftop equipment placement

Week of 8/20/18

  • Spray foam insulation applied in lower level garage
  • Roofing begins
  • Boiler equipment installation continues
  • Cooling towers hoisted to roof

Week of 8/27/18

  • Hoist erected
  • Masonry parapet and exterior enclosure begins
  • Masonry begins on North and West elevations
  • Concrete company ships out

The Belmont Village tower crane will be dismantled the week of August 27th OR September 3rd. Date confirmation and logistics details will be shared later this month.

Thank you for your continued patience and understanding as we work through these critical steps of construction. Should you have questions or would like additional information about the Belmont Village project, please contact Adam Hamilton of Belmont Village or Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.

To choose the updates that you'd like to receive about The Lincoln Common development, please update your preferences at LincolnCommon.com.