Belmont Village Construction Progress Update

Go Back

BV_121418.jpg#asset:1026

Week of 12/17/18

  • Mechanical, electrical, and plumbing throughout building continues
  • Exterior masonry west
  • 7th floor interior metal stud wall framing
  • Penthouse metal panel enclosure
  • Install windows
  • Construct elevators

Week of 12/24/18

  • Mechanical, electrical, and plumbing throughout building continues
  • Exterior masonry west
  • 7th floor interior metal stud wall framing
  • Penthouse metal panel enclosure
  • Install windows
  • Construct elevators

Week of 12/31/18

  • Mechanical, electrical, and plumbing throughout building continues
  • Exterior masonry west
  • Install windows
  • Construct elevators

Week of 1/7/18

  • Mechanical, electrical, and plumbing throughout building continues
  • Exterior masonry west
  • Rock/tape drywall
  • Install windows
  • Construct elevators

Thank you for your continued patience and understanding as we work through construction. Should you have questions or would like additional information about the BelmontVillage project, please contact Adam Hamilton of Belmont Village or Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.