The Lincoln Common Construction Update - August 25, 2017
Posted on August 25, 2017
Week of 8/28/17
- Tower crane install for the A2 south tower is complete (see below progress photos)
- Excavation work will continue on site
- Earth retention system install will continue
- Concrete work for the foundations in the A2 South Tower will continue
- Concrete work for the foundations in the A1 North Tower will start
- Pedestrian canopy on Fullerton has been completed
Week of 9/4/17
- Excavation work will continue on site
- Earth retention system install will continue
- Concrete work for the foundations in the A2 South Tower will continue
- Concrete work for the foundations in the A1 North Tower will continue
Week of 9/11/17
- Excavation work will continue on site
- Earth retention system install will continue
- Concrete work for the foundations in the A2 South Tower will continue
- Concrete work for the foundations in the A1 North Tower will continue
- Foundation for the A1 North tower crane will be poured
- Storm water utility work will start; see traffic control plans for work dates and locations on each Lincoln, Fullerton and Orchard.
We appreciate your patience and understanding as we bring The Lincoln Common to life! Please visit LincolnCommon.com for additional project details.