The Lincoln Common Construction Progress Update - September 18, 2017

Posted on September 18, 2017


Lincoln Common - View 1-September 18th, 2017, 829 am.jpg#asset:875

Week of 9/18/17

  • Excavation work will continue on site
  • The tower crane for the A1 North Tower will be installed this week
  • Concrete work for the foundations in the A2 South Tower will continue
  • Concrete work for the foundations in the A1 North Tower will start
  • The site utility storm sewer work will be completed this week
  • Site utility storm water work on Fullerton will be started this week

Week of 9/25/17

  • Excavation work will continue on site
  • Earth retention system install will continue
  • Site utility storm sewer work on Fullerton will continue
  • Concrete work on the A2 South Tower will continue
  • Concrete work on the A1 North Tower will continue

Week of 10/2/17

  • Excavation work will continue on site
  • Earth retention system install will continue
  • Concrete work on the A2 South Tower will continue
  • Concrete work on the A1 North Tower will continue
  • Site utility storm sewer work on Lincoln will be started

Thank you for your continued patience and understanding as we work through these critical first steps of construction. To choose the updates that you'd like to receive about The Lincoln Common development, please update your preferences at LincolnCommon.com.

Lincoln Common - View 4-September 18th, 2017, 818 am.jpg#asset:882