The Lincoln Common Construction Progress Update - August 9, 2017

Posted on August 09, 2017

Week of 8/7/17

  • Drilled pier foundation work will be completed
  • Excavation work will continue on site
  • Earth retention system install will be started

Week of 8/14/17

  • Excavation work will continue on site
  • Earth retention system install will continue
  • The tower crane foundation for the South tower will be poured

Week of 8/21/17

  • Excavation work will continue on site
  • Earth retention system install will continue
  • Pedestrian Canopy will be installed on the Fullerton sidewalk as shown on the Phase 2 Logistics Plan
  • We will be closing Lincoln Ave from Orchard to the entrance of the parking garage on 8/23, 8/24 and 8/25 for the installation of the tower crane for the South tower. See the below drawing showing the street closure. The sidewalk on the West side of Lincoln will remain open for pedestrians.

We appreciate your patience and understanding as The Lincoln Common comes to life! Please visit LincolnCommon.com for additional project details and future updates.