Professional Building Facade Restoration to Begin Week of May 8th

Posted on May 05, 2017

The façade of the Dental Professional Building at 2358 North Lincoln Avenue will be incorporated into a new, mixed-use structure. This historic façade will be dismantled and preserved through a detailed inventory of all components. The preserved façade will be rebuilt into the new structure and will include all of the existing details.

Timing and sequence of work (approx. 12 weeks):

Week of May 8th

  • Install temporary construction fence
  • Install scaffolding and protection
  • Begin removal and inventory of the façade elements

Week of June 19th

  • The process of salvaging and storing the façade materials on site will be ongoing for approximately 6 weeks

Week of July 24th

  • Remove scaffolding
  • The remainder of the building will be demolished once dismantling of the façade is complete

Construction Commencement

We anticipate receiving the new structure building permit from the City of Chicago in the month of May