Lincoln Common Construction Progress Update - October 20, 2017

Posted on October 20, 2017


Lincoln Common - View 3-October 18th, 2017, 944 am.jpg#asset:880

Thank you for accommodating last week's utility work and street closure! All utility storm water work on Fullerton was completed as scheduled without issue.

Week of 10/16/17 through week of 10/31/17

  • Excavation work will continue on site
  • Concrete work for the foundations in the A2 South Tower will continue
  • Concrete work for the foundations in the A1 North Tower will continue

Your continued patience and understanding is highly appreciated as we work through these critical steps of construction. To choose the updates that you'd like to receive about The Lincoln Common development, please update your preferences at LincolnCommon.com.