Lincoln Common Construction Progress Update - November 3, 2017

Posted on November 03, 2017

Lincoln-Common-View-2-November-3rd-2017-744-am.jpg#asset:809

Week of 11/6/17

  • Excavation work will continue on site
  • Concrete work for the foundations in the A2 South Tower will continue
  • Concrete work for the foundations in the A1 North Tower will continue
  • Under slab plumbing and electrical will continue in the basements of both towers

Week of 11/13/17

  • Excavation work will continue on site
  • Concrete work on the A2 South Tower will continue
  • Basement slab on grade concrete in A2 will be poured
  • Concrete work on the A1 North Tower will continue

Week of 11/20/17

  • Excavation work will continue on site
  • Concrete work on the A2 South Tower will continue
  • 1st floor deck framing on A2 will start
  • Concrete work on the A1 North Tower will continue

We appreciate your continued patience and understanding as The Lincoln Common comes to life! Please visit LincolnCommon.com for additional project details and future updates.