Lincoln Common Construction Progress Update - November 21, 2017

Posted on November 21, 2017

Lincoln Common - View 2-November 20th, 2017, 831 am.jpg#asset:876


Week of 11/20/17

  • Excavation work will continue on site
  • Concrete work on the A2 South Tower will continue
  • 1st floor deck framing on A2 will start
  • Concrete work on the A1 North Tower will continue

Week of 11/27/17

  • Excavation work will continue on site
  • Concrete work on the A2 South Tower will continue
  • Basement slab on grade concrete in A2 will be poured
  • Concrete work on the A1 North Tower will continue
  • Excavation prep work for the D building West of the parking garage will start

Week of 12/4/17

  • Excavation work will continue on site
  • Concrete work on the A2 South Tower will continue
  • 1st floor deck framing on A2 will be poured
  • Concrete work on the A1 North Tower will continue

We appreciate your continued patience and understanding as The Lincoln Common comes to life! Please visit LincolnCommon.com for additional project details and future updates.