Installation of earth retention bracing at Tier 1 is complete. Excavation down to Tier 2 is underway.

Week of 10/30/17 through week of 11/20/17

  • Excavation down to Tier 2
  • Earth Retention – Waler and Bracing Installation for Tier 2