Belmont Village Lincoln Park Construction Progress Update, Dec. 18, 2017

Posted on December 18, 2017

BV_121817.jpeg#asset:827

Excavation of the site is ongoing. The concrete operation has mobilized and placement of grade beams has started. Underground plumbing and underground electrical work will begin in the coming days.

Week of 12/18/17

  • Excavation
  • Concrete
  • Underground Plumbing Installation

Week of 12/25/17

  • Excavation
  • Concrete
  • Underground Plumbing Installation
  • Underground Electrical Installation

Week of 1/1/18

  • Excavation
  • Concrete
  • Underground Plumbing Installation
  • Underground Electrical Installation

Week of 1/8/18

  • Excavation
  • Concrete
  • Underground Plumbing Installation
  • Underground Electrical Installation

Thank you for your continued patience and understanding as we work through these critical first steps of construction. Should you have questions or would like additional information about the Belmont Village project, please contact Adam Hamilton of Belmont Village or Dean Psarros, W.E. O'Neil Construction Liaison for Belmont Village Lincoln Park.