Belmont Village Demolition & Construction Update - May 1, 2017

Posted on May 01, 2017

  • Demolition was completed on March 3, 2017.
  • The City of Chicago building permit was issued on March 24, 2017.
  • Inclinometer installation in the alley was completed on April 6, 2017.
  • Today, Monday, May 1, 2017, we are scheduled to start the underpinning work on the foundations of the adjoining properties to the North and West of the site. This work is currently scheduled to be completed in approximately 5 weeks.
  • Excavation and site work is expected to begin once the underpinning work is completed.
  • Fullerton Ave. and Orchard St. sidewalks and parking lanes have been closed and will remain closed for the duration of the project.

Thank you for your continued patience and understanding as we work through these critical first steps of construction. Should you have questions or would like additional information, please reach out to the Senior Living or Construction representatives on the Contact page.