Lincoln Common Construction Progress Update - December 8, 2017

Happy Holidays from the Lincoln Common Development Team! 

D-building-Demo-in-front-of-the-Garage-12.5.17.jpg#asset:821

Week of 12/11/17

  • Excavation work will continue on site
  • Concrete work on the A2 South Tower will continue – Decking for the 2nd floor will continue
  • Concrete work on the A1 North Tower will continue – Decking for the 1st floor will start
  • D Building work North of the garage – Caisson foundation work will start. We will be removing the trees, plantings and planters from in front of the North parking garage entrance to accommodate the caisson drill rig. (See map above.)  

Week of 12/18/17

  • Excavation work will continue on site
  • Concrete work on the A2 South Tower will continue – 2nd floor deck will be poured and 3rd floor decking will start
  • Concrete work on the A1 North Tower will continue – Decking for the 1st floor will continue. Sections of the loading dock basement slab will be poured.
  • D Building work North of the garage – Caisson foundation work will be complete. Sewer work in Lincoln Avenue will start.

Week of 12/25/17

  • Excavation work will continue on site
  • Concrete work on the A2 South Tower will continue –3rd floor deck will be poured
  • Concrete work on the A1 North Tower will continue –1st floor deck will be poured. More of the loading dock basement slab will be poured.
  • D Building work North of the garage – Sewer work on Lincoln Avenue will start. Partial lane closure may occur.
  • Installation of the storm water detention tank under the building footprint will start.

We appreciate your continued patience and understanding as The Lincoln Common comes to life! Please visit LincolnCommon.com for additional project details and future updates.   More

Reminder: Fullerton Ave Closure 12/6 through 12/8

BV_120117.png#asset:818

Belmont Village will begin its tower crane install tomorrow, Wednesday, December 6. Work will continue through Friday, December 8. Fullerton Avenue between Orchard and Burling Streets will be CLOSED during this time(see above map). Reminders of the closure have been posted throughout the area.